L6M5 practice question 8 of 15

A local library is contracting a construction firm to design and build a new extension using a target costing method. Which of the following statements are true about this pricing mechanism? Select all that apply

Full set: 83 questions
Answer options
A: any cost savings will be enjoyed by the library
B: this form of contract requires a collaborative relationship Correct answer
C: a target cost will ensure the contractor works competitively against the library to ensure costs remain low and their profit margin remains high
D: the contractor is a price setter
Correct Answer:
B. this form of contract requires a collaborative relationship
Explanation

Target costing requires a collaborative relationship between the client and contractor. The other options do not accurately describe the target costing approach.

Scroll to Top