L6M5 practice question 10 of 15

Which of the following is an advantage to the contractor in an EPC contract arrangement? EPC contracts provide several benefits to contractors, such as clear project scope, reduced risks, and better project management. Answer Options:

Full set: 83 questions
Answer options
A: The scope is clearly defined by the client Correct answer
B: There is an early completion bonus
C: There are no subcontractors to manage
D: The client assumes all risks for the construction
Correct Answer:
A. The scope is clearly defined by the client
Explanation

The correct answer is 1 (p.13). The scope is clearly defined by the client, making it easier for the contractor to plan and execute the project efficiently. Option 2 is incorrect because not all EPC contracts offer an early completion bonus. Option 3 is incorrect because EPC contracts can include subcontractors. Option 4 is incorrect because risks are shared between the client and contractor. [P.13]

Scroll to Top