LEED-AP-BDC practice question 28 of 35

A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?

Full set: 305 questions
Answer options
A: No action is necessary as the PV system is not required to be commissioned
B: The PV system installer should commission his own installations and share the results with the project owner
C: The Cx agent for the project must conduct or oversee the Cx of the PV system Correct answer
D: The building's mechanical engineer should commission his own installations and share the results with the project owner
Correct Answer:
C. The Cx agent for the project must conduct or oversee the Cx of the PV system
Explanation

The Energy and Atmosphere (EA) Prerequisite, Fundamental Commissioning and Verification, requires that all of the building’s energy-related systems be commissioned. This scope explicitly includes renewable energy systems such as the Photovoltaic (PV) system mentioned. The commissioning process must be led and reviewed by a Commissioning Authority (CxA) who has documented commissioning experience and is independent of the project's design and construction management. The CxA is responsible for conducting or overseeing the commissioning of these systems to verify they are installed and performing correctly.

Why Incorrect

A. This is incorrect; the prerequisite explicitly includes renewable energy systems in the scope of required commissioning activities.
B. The installer cannot commission their own work without independent oversight from the CxA, as this represents a conflict of interest.
D. The mechanical engineer is part of the design team and therefore cannot act as the independent CxA for their own design or related systems.

References

1. U.S. Green Building Council. (2014). LEED v4 for Building Design and Construction Reference Guide. Washington, DC: U.S. Green Building Council. Page 358, "EA Prerequisite: Fundamental Commissioning and Verification," Step-by-Step Guidance, lists "renewable energy systems" as systems to be commissioned.

2. U.S. Green Building Council. (2021). LEED v4.1 Building Design and Construction. "EA Prerequisite: Fundamental Commissioning and Verification," Commissioned Systems section.

3. ASHRAE. (2013). ASHRAE Guideline 0-2013, The Commissioning Process. This standard, referenced by LEED, outlines the roles and responsibilities of the Commissioning Authority.