LEED-AP-BDC practice question 28 of 35
A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?
Full set: 305 questionsThe Energy and Atmosphere (EA) Prerequisite, Fundamental Commissioning and Verification, requires that all of the building’s energy-related systems be commissioned. This scope explicitly includes renewable energy systems such as the Photovoltaic (PV) system mentioned. The commissioning process must be led and reviewed by a Commissioning Authority (CxA) who has documented commissioning experience and is independent of the project's design and construction management. The CxA is responsible for conducting or overseeing the commissioning of these systems to verify they are installed and performing correctly.
A. This is incorrect; the prerequisite explicitly includes renewable energy systems in the scope of required commissioning activities.
B. The installer cannot commission their own work without independent oversight from the CxA, as this represents a conflict of interest.
D. The mechanical engineer is part of the design team and therefore cannot act as the independent CxA for their own design or related systems.
1. U.S. Green Building Council. (2014). LEED v4 for Building Design and Construction Reference Guide. Washington, DC: U.S. Green Building Council. Page 358, "EA Prerequisite: Fundamental Commissioning and Verification," Step-by-Step Guidance, lists "renewable energy systems" as systems to be commissioned.
2. U.S. Green Building Council. (2021). LEED v4.1 Building Design and Construction. "EA Prerequisite: Fundamental Commissioning and Verification," Commissioned Systems section.
3. ASHRAE. (2013). ASHRAE Guideline 0-2013, The Commissioning Process. This standard, referenced by LEED, outlines the roles and responsibilities of the Commissioning Authority.
Keep practicing
Take the free LEED-AP-BDC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-BDC practice questions
- Question 1When required to measure residential and non-residential densities, Location and Transpor…
- Question 2A design team is working on a hospital project. In order to meet the Energy and Atmospher…
- Question 3For Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan,…
- Question 4What LEED Building Design and Construction rating system mandates a preliminary LEED meet…
- Question 5Which of the following strategies would be considered an acceptable minor improvement wit…
- Question 6Which of the following sinks is classified as a private lavatory faucet under Water Effic…