LEED-AP-BDC practice question 1 of 35

When required to measure residential and non-residential densities, Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to measure the residential and non-residential densities in what way?

Full set: 305 questions
Answer options
A: Measure densities within a 1/4 mi. (0.40 km) radius of the project boundary Correct answer
B: Measure densities within a 1/2 mi. (0.80 km) radius of the project boundary
C: Measure densities within a 1/3 mi. (0.53 km) radius of the project boundary
D: Measure densities within a 3/4 mi. (1.20 km) radius of the project boundary
Correct Answer:
A. Measure densities within a 1/4 mi. (0.40 km) radius of the project boundary
Explanation

The Location and Transportation (LT) credit for Surrounding Density and Diverse Uses, Option 1: Surrounding Density, requires the project to be located on a site with a specified minimum density. The credit language explicitly states that this density must be measured "within a 1/4-mile (400-meter) radius of the project boundary." The calculation includes existing, publicly accessible residential and non-residential buildings and does not include the area of the project site itself.

Why Incorrect

B. A 1/2-mile (800-meter) radius is the distance used for other LT credits, such as Access to Quality Transit, not for measuring surrounding density.
C. A 1/3-mile radius is not a standard measurement distance used for density calculations within the LEED v4 rating system.
D. A 3/4-mile radius is not a standard measurement distance used for density calculations within the LEED v4 rating system.

References

1. U.S. Green Building Council. (2014). LEED v4 for Building Design and Construction. Washington, DC: U.S. Green Building Council. Page 78, "LT Credit: Surrounding Density and Diverse Uses," "Option 1. Surrounding Density."

2. U.S. Green Building Council. (2014). LEED v4 for Building Design and Construction. Washington, DC: U.S. Green Building Council. Page 81, "Step-by-Step Guidance," "Option 1. Surrounding Density," Step 1, which details the 1/4-mile radius requirement.