LEED-AP-BDC practice question 14 of 35

A project team seeking certification for a new school is attempting to achieve Materials and Resources Credit, Construction and Demolition Waste Management, Option 2. Reduction of Total Waste Material. What strategy can be taken to meet the requirements of this credit?

Full set: 305 questions
Answer options
A: Track waste materials per occupant
B: Track waste materials used on site
C: Document total waste by project cost
D: Document total waste per building floor area Correct answer
Correct Answer:
D. Document total waste per building floor area
Explanation

The LEED v4 BD+C MR Credit: Construction and Demolition Waste Management, Option 2 (Reduction of Total Waste Material) requires the project team to limit the total amount of construction waste generated. The specific threshold for achieving this credit is generating no more than 2.5 pounds of waste per square foot (12.2 kilograms per square meter) of the building's floor area. Therefore, documenting the total waste generated per unit of building floor area is the required tracking methodology.

Why Incorrect

A. Tracking waste per occupant is a metric for ongoing operational waste, not construction waste.
B. This is too vague; the credit requires tracking waste generated, not all materials used on site.
C. The credit's threshold is based on weight per area (mass/area), not the cost of the project.

References

1. U.S. Green Building Council. (2014). LEED v4 for Building Design and Construction. Washington, DC: U.S. Green Building Council. p. 558, "MR Credit: Construction and Demolition Waste Management, Credit Requirements, Option 2. Reduction of Total Waste Material."