LEED-AP-BDC practice question 12 of 35

Which item is included in the reuse calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction?

Full set: 305 questions
Answer options
A: Floor decking Correct answer
B: Asbestos insulation
C: Exterior glazing
D: Plumbing fixtures
Correct Answer:
A. Floor decking
Explanation

The LEED v4.1 BD+C credit for Building Life-Cycle Impact Reduction, Option 1 Building and Material Reuse, calculates the percentage of a building's surface area that is reused. The calculation includes structural elements like floor decking, columns, and beams, as well as the building enclosure. It explicitly excludes items that are typically replaced during a renovation for performance or safety reasons, such as hazardous materials, window assemblies, and MEP (Mechanical, Electrical, and Plumbing) systems and fixtures. Therefore, floor decking is a qualifying structural component for the reuse calculation.

Why Incorrect

B. Asbestos insulation: This is a hazardous material, which is explicitly excluded from the reuse calculation for safety and liability reasons.
C. Exterior glazing: Window assemblies are part of the building envelope but are often excluded from the calculation if replaced, as is common for energy performance upgrades.
D. Plumbing fixtures: These are considered part of the plumbing system (MEP) or as fixtures (FF&E), both of which are excluded from the reuse calculation.

References

1. U.S. Green Building Council. (2020). LEED v4.1 Building Design and Construction Reference Guide. "MR Credit: Building Life-Cycle Impact Reduction," Option 1. Building and Material Reuse, page 578. The guide specifies, "The calculation includes the building's structure... and enclosure... Exclude from the calculation window assemblies... and hazardous materials."

2. The Catholic University of America, School of Architecture and Planning. (n.d.). Course A&P 632: Comprehensive Building Design Studio. Course materials on LEED v4 MR Credits specify that reuse calculations focus on the building's primary structure and envelope, excluding MEP and hazardous materials.