LEED-AP-BDC practice question 24 of 35
Which of the following documents contains the design team's interpretation of the Owner's Project Requirements?
Full set: 305 questionsThe Basis of Design (BOD) is a formal document that explains how the design of the building systems meets the Owner's Project Requirements (OPR). The OPR defines the project's goals and functional requirements from the owner's perspective. The BOD is the design team's technical response, detailing the systems, components, and methods chosen to achieve those goals. This documentation is a core component of the commissioning process outlined in the Energy and Atmosphere prerequisite, Fundamental Commissioning and Verification.
B. A Simple Box Energy Model is an early-stage analysis tool, not the formal response to the OPR.
C. A system's manual is a post-construction document for building operators, detailing system operation and maintenance.
D. An Integrated Project Delivery (IPD) report would document the IPD process, not the specific technical response to the OPR.
1. U.S. Green Building Council. (2020). LEED v4.1 Building Design and Construction Reference Guide. Washington, DC: U.S. Green Building Council. "EA Prerequisite: Fundamental Commissioning and Verification," Step 2: Develop the OPR and BOD, p. 398.
2. Portland State University, M.S. in Mechanical Engineering Courseware. (n.d.). ME 521: Building Energy Modeling. "Commissioning Process." The course materials describe the relationship where the BOD documents the design team's approach to meeting the OPR.
Keep practicing
Take the free LEED-AP-BDC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-BDC practice questions
- Question 1When required to measure residential and non-residential densities, Location and Transpor…
- Question 2A design team is working on a hospital project. In order to meet the Energy and Atmospher…
- Question 3For Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan,…
- Question 4What LEED Building Design and Construction rating system mandates a preliminary LEED meet…
- Question 5Which of the following strategies would be considered an acceptable minor improvement wit…
- Question 6Which of the following sinks is classified as a private lavatory faucet under Water Effic…