LEED-AP-BDC practice question 24 of 35

Which of the following documents contains the design team's interpretation of the Owner's Project Requirements?

Full set: 305 questions
Answer options
A: Basis of Design (BOD) Correct answer
B: Simple Box Energy Model Analysis
C: System's manual
D: Integrated Project Delivery report
Correct Answer:
A. Basis of Design (BOD)
Explanation

The Basis of Design (BOD) is a formal document that explains how the design of the building systems meets the Owner's Project Requirements (OPR). The OPR defines the project's goals and functional requirements from the owner's perspective. The BOD is the design team's technical response, detailing the systems, components, and methods chosen to achieve those goals. This documentation is a core component of the commissioning process outlined in the Energy and Atmosphere prerequisite, Fundamental Commissioning and Verification.

Why Incorrect

B. A Simple Box Energy Model is an early-stage analysis tool, not the formal response to the OPR.
C. A system's manual is a post-construction document for building operators, detailing system operation and maintenance.
D. An Integrated Project Delivery (IPD) report would document the IPD process, not the specific technical response to the OPR.

References

1. U.S. Green Building Council. (2020). LEED v4.1 Building Design and Construction Reference Guide. Washington, DC: U.S. Green Building Council. "EA Prerequisite: Fundamental Commissioning and Verification," Step 2: Develop the OPR and BOD, p. 398.

2. Portland State University, M.S. in Mechanical Engineering Courseware. (n.d.). ME 521: Building Energy Modeling. "Commissioning Process." The course materials describe the relationship where the BOD documents the design team's approach to meeting the OPR.