LEED-AP-BDC practice question 20 of 35
Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?
Full set: 305 questionsThe Materials and Resources (MR) Prerequisite, Construction and Demolition Waste Management Planning, requires the development and implementation of a waste management plan. The general contractor is directly responsible for managing construction activities and waste streams on-site. Integrating the contractor early in the design phase allows them to provide crucial input on the feasibility, methods, and costs associated with diverting specific materials from the landfill, ensuring the plan is realistic and effective. Their expertise is essential for identifying local recycling facilities and planning logistics for material separation and hauling.
A. The owner sets project goals and provides direction but is not directly involved in the day-to-day implementation of the waste management plan.
C. Occupants are end-users of the completed building and are not involved in the construction process or its waste management planning.
D. The facility manager is responsible for the building's operation and maintenance post-construction, not during the construction phase.
1. U.S. Green Building Council. (2014). LEED v4 for Building Design and Construction Reference Guide. Washington, DC: U.S. Green Building Council. p. 519, "Step-by-Step Guidance, Step 1. Determine waste management strategy."
2. Kibert, C. J. (2016). Sustainable Construction: Green Building Design and Delivery (4th ed.). Wiley. Chapter 11, "Construction and Demolition Waste Management," discusses the contractor's central role in planning and execution.
Keep practicing
Take the free LEED-AP-BDC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-BDC practice questions
- Question 1When required to measure residential and non-residential densities, Location and Transpor…
- Question 2A design team is working on a hospital project. In order to meet the Energy and Atmospher…
- Question 3For Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan,…
- Question 4What LEED Building Design and Construction rating system mandates a preliminary LEED meet…
- Question 5Which of the following strategies would be considered an acceptable minor improvement wit…
- Question 6Which of the following sinks is classified as a private lavatory faucet under Water Effic…