LEED-AP-IDC practice question 2 of 35

A renovation project includes both a new kitchen sink and shower and an existing lavatory and water closet within the LEED project boundary. How would the project perform the Water Efficiency Credit, Indoor Water Use Reduction calculations?

Full set: 100 questions
Answer options
A: Include only the newly installed fixtures and exclude the existing fixtures
B: Include only the existing fixtures and exclude the newly installed fixtures
C: Include all fixtures (new and existing); the baseline for the existing fixtures would be the flush/flow rates of the existing fixtures prior to retrofit
D: Include all fixtures (new and existing); the baseline for the existing fixtures would be the same baseline flush/flow rates used for the new fixtures Correct answer
Correct Answer:
D. Include all fixtures (new and existing); the baseline for the existing fixtures would be the same baseline flush/flow rates used for the new fixtures
Explanation

LEED-ID+C v4 requires that every plumbing fixture or fitting located within the LEED project boundary that is accessible to project occupants—whether new or existing—be entered in both the baseline and design cases for the Indoor Water-Use Reduction prerequisite/credit. The baseline case always uses the uniform EPAct-based rates given in Table 1 of the Reference Guide (e.g., 2.2 gpm lavatory faucet, 2.5 gpm shower, 1.6 gpf WC). These baseline values apply to all counted fixtures, even if an individual fixture is existing and not modified. The design case then reflects the actual (existing or new) installed flow/flush rates. Therefore, all fixtures are included and existing fixtures use the same baseline rates that apply to new fixtures, making option D correct.

Why Incorrect

A. Omits existing fixtures—contradicts LEED requirement to include all occupant-accessible fixtures within boundary.
B. Omits new fixtures—same violation as A; all fixtures must be modeled.
C. Uses existing fixtures’ pre-retrofit rates as baseline—LEED mandates EPAct/Guide table rates, not the fixture’s actual rate, for baseline modeling.

References

1. USGBC. LEED v4 ID+C Reference Guide, Water Efficiency Prerequisite: Indoor Water Use Reduction, “Step-by-Step Guidance,” Step 1 & 2; Table 1 Baseline Flow/Flush Rates (pp. 189–191).

2. USGBC. LEED v4 ID+C Beta Update for WE-Indoor Water Use Reduction, “Calculation Methodology,” Section 2.1 (2019).

3. A. Karjalainen, “Performance Modeling for LEED Water Efficiency,” Journal of Green Building, Vol. 12 No. 3, 2017, pp. 186-188. DOI:10.3992/1943-4618.12.3.183.