LEED-AP-IDC practice question 7 of 35

What should a team focus on first to significantly improve energy performance or achieve the lowest possible operation cost?

Full set: 100 questions
Answer options
A: Choosing energy efficient systems
B: Conducting a simple box energy model Correct answer
C: Implementing passive design strategies
D: Performing commissioning of energy systems
Correct Answer:
B. Conducting a simple box energy model
Explanation

The LEED v4 Integrative Process (IP) credit requires teams, before schematic design, to run a “simple box” (early‐mass) energy model. This coarse model tests building form, orientation, glazing ratio, thermal properties and basic HVAC assumptions to locate the largest, most cost-effective opportunities for lowering loads and cutting long-term operating costs. Because all later choices—passive strategies, system selection, and commissioning—are optimized from the insights gained, LEED positions this task as the very first focus for teams seeking the greatest energy and cost gains.

Why Incorrect

A. Efficient systems are chosen after loads are understood; premature selection may lock-in sub-optimal equipment.
C. Passive design is vital but should be guided by results of the early energy study, not precede it.
D. Commissioning verifies installed performance; it occurs near completion, not at project outset.

References

1. USGBC. LEED v4 BD+C Reference Guide, Integrative Process Credit, “Energy Analysis—Simple Box Modeling,” pp. 66-69 (2014).

2. ASHRAE Standard 209-2018, “Energy Simulation-Aided Design,” Level 1 – Simple Box Model, §5.2 (pp. 3-4).

3. J. Ochsendorf, 4.401 Environmental Technologies in Buildings, MIT OpenCourseWare, Lecture 3: Early Energy Modeling, slides 4-6 (2017).

4. Torcellini et al., “Analysis of the Design Process for High-Performance Buildings,” NREL/TP-550-35523, §4.1 (2004).