A tenant moving into an existing building will need to install new HVAC, power, lighting systems and other equipment. Which of the following resources would help the tenant meet the requirements of Energy and Atmosphere Credit, Optimize Energy Performance?
Full set: 100 questionsEnergy and Atmosphere (EA) Credit “Optimize Energy Performance” in LEED-ID+C v4 requires the project to demonstrate energy cost savings relative to a baseline building modeled in accordance with ANSI/ASHRAE/IES Standard 90.1-2010. All performance calculations, prescriptive options, and compliance forms reference this standard; therefore, familiarity with 90.1-2010 is essential for a tenant designing new HVAC, power, and lighting systems to meet the credit requirements.
A. Green Seal Standard 11 governs low-VOC paints and coatings; it applies to Indoor Environmental Quality, not energy performance.
B. ASHRAE 62.1-2010 addresses minimum ventilation rates for IAQ, not energy optimization metrics.
D. SCAQMD rules set VOC limits for adhesives and sealants; they relate to Low-Emitting Materials, not EA energy savings.
1. USGBC. LEED v4 for Interior Design and Construction Reference Guide, Energy & Atmosphere, “Optimize Energy Performance,” p. 205-210 (baseline compliance cites ASHRAE/IES 90.1-2010 throughout).
2. ASHRAE. ANSI/ASHRAE/IES Standard 90.1-2010, §11 & Appendix G (whole-building energy modeling procedures used by LEED).
3. USGBC. LEED v4 ID+C Reference Guide, Indoor Environmental Quality, “Low-Emitting Materials,” p. 459 (lists Green Seal-11 and SCAQMD as VOC references, not energy).
4. ASHRAE. ANSI/ASHRAE Standard 62.1-2010, §4-6 (ventilation requirements; cited in IEQ credits, not EA).
Keep practicing
Take the free LEED-AP-IDC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other LEED-AP-IDC practice questions
- Question 1A mechanical engineer needs to identify spaces that are considered densely occupied accor…
- Question 2A renovation project includes both a new kitchen sink and shower and an existing lavatory…
- Question 3A project team wants to achieve Materials and Resources Credit, Building Product Disclosu…
- Question 4To satisfy the Increased Ventilation strategy in the Indoor Environmental Quality Credit,…
- Question 5A tenant implements the following strategies to reduce the amount of water used. Which st…
- Question 7What should a team focus on first to significantly improve energy performance or achieve …