MSP-PRACTITIONER practice question 5 of 15
Which of the following is not an Input to delivering the capability?
Full set: 75 questionsIn MSP, “Deliver the Capabilities” is the process that coordinates projects so the programme can obtain the capabilities described in the Blueprint. Its documented inputs (AXELOS, MSP 2011 ed., Table 14.1 “Inputs to Deliver the Capability”) are the approved Project Dossier, Blueprint, Tranche/Programme Plans, Benefit information and other governance baselines. Project outputs are created by, not supplied to, this process; they are listed in the same table as outputs of the process. Therefore, Project outputs are not an input, whereas the Project Dossier, Business Case (the live justification baseline carried forward into every process), and Blueprint all precede and guide capability delivery.
B. Project dossier – listed as an explicit input to Deliver the Capability (MSP 2011 ed., p. 197).
C. Business Case – retained as a baseline and referenced in every transformational-flow process, hence an input (MSP 2011 ed., p. 90 & p. 197).
D. Blueprint – provides the target-state design and is an input to Deliver the Capability (MSP 2011 ed., p. 197).
1. AXELOS. “Managing Successful Programmes
” 2011 edition
Table 14.1 “Inputs to Deliver the Capability”
pp. 197-198.
2. AXELOS. “Managing Successful Programmes
” 2011 edition
§6.3 “Programme Business Case – live baseline”
p. 90.
3. University of Warwick WMG. “Programme Management (MSP) Lecture Notes
” session 5
slide 18 – Inputs to Deliver the Capability.
Keep practicing
Take the free MSP-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other MSP-PRACTITIONER practice questions
- Question 1Which of the following will not be in Issue register?
- Question 2Select the best option defined by following sentence: 'Action of carrying out the coordin…
- Question 3Through which document programmes establish the context in which risks will be identified…
- Question 4For a programme that focuses on Political and societal change which scenario will lead to…
- Question 6Which of the following statements best defines 'transformational Flow'?
- Question 7Which of the following defines Dis-benefit?