An administrator intends to configure a NearSync replication schedule with a 15-minute Recovery Point Objective (RPO) on a hybrid 3-node cluster. The current nodes in the cluster are configured with one SSD and four HDDs each. Which cost-effective modification is required to support this specific replication schedule?
Full set: 109 questionsNearSync replication on hybrid clusters requires a minimum of 2 SSDs per node to handle the metadata operations and provide sufficient performance for frequent snapshots. With only 1 SSD per node, the cluster cannot support NearSync's performance requirements. Adding a second SSD to each node is the most cost-effective solution that directly addresses the minimum hardware requirement for NearSync on hybrid configurations.
A. Replacing HDDs with NVMe is excessive and not cost-effective for this requirement.
B. Three nodes meet the minimum cluster size for NearSync replication.
C. Default CVM memory is sufficient for NearSync; increasing to 64GB is unnecessary.
1. Nutanix Bible - Data Protection Section, NearSync Requirements
2. Nutanix Best Practices Guide - Hybrid Cluster Configuration for Replication
3. Nutanix Hardware Platform Specifications - SSD Requirements for Data Protection Features
4. Nutanix Data Protection and Disaster Recovery Solution Guide - NearSync Hardware Prerequisites
5. Nutanix Tech Note TN-2089 - Hybrid Cluster Design for Business Continuity
Keep practicing
Take the free NCP-BC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other NCP-BC practice questions
- Question 1When designing a Disaster Recovery strategy to an NC2 cluster using MST, which technical …
- Question 2An organization uses Nutanix Disaster Recovery with automatic virtual network creation in…
- Question 3An administrator configures disaster recovery between an on-premises AZ and a Nutanix Clo…
- Question 4An administrator needs to provide leadership with a report showing the timeframe of each …
- Question 5After a failover and stabilization of workloads at the recovery AZ, an administrator remo…
- Question 6An administrator executes an Unplanned Failover of web server VMs from an on-premises AZ …