NCP-BC practice question 15 of 25

What must an administrator verify before starting a migration of entities from a protection domain to a protection policy?

Full set: 109 questions
Answer options
A:

A. The entities must be added to a category in Prism Central.

B:

B. The recovery plan must be active.

C:

C. The entities must have no ongoing replication tasks.

Correct answer
D:

D. A full backup of the protection domain must be completed.

Correct Answer:
C. C. The entities must have no ongoing replication tasks.
Explanation

The migration process from a legacy Protection Domain to a modern Protection Policy involves changing the underlying data protection configuration for the specified entities (VMs or Volume Groups). To ensure a consistent and successful transition, the system requires that no replication tasks are in progress for these entities. An active replication could interfere with the migration wizard's ability to reconfigure the protection schedule and targets, potentially leading to a failed migration or an inconsistent protection state. Therefore, pausing or waiting for ongoing replications to complete is a mandatory prerequisite.

Why Incorrect

A. Adding entities to a category is part of the new Protection Policy configuration, not a prerequisite for starting the migration from the old system.
B. A recovery plan is associated with the destination Protection Policy, which does not exist until after the migration is configured.
D. While having a recent backup is a good operational practice, it is not a technical prerequisite enforced by the system to initiate the migration process.

References

- Nutanix Disaster Recovery Guide v6.0, Chapter: "Migrating from Asynchronous and NearSync Replication to Nutanix Disaster Recovery", Section: "Migrating Entities from a Protection Domain to a Protection Policy", Prerequisite list. The documentation explicitly states, "Ensure that there are no ongoing replications for the entities you want to migrate."