A global financial system is being delivered by the program team to allow access from anywhere in the world. Following a new cross-border regulation…
Full set: 452 questionsThe new regulation and the subsequent CEO request for an audit represent a significant, unplanned event that impacts the program. According to standard program management practices, the first and most critical step when faced with such a change is to conduct a thorough impact analysis. This assessment will determine the effects of the additional work on the program's schedule, budget, resources, risks, and, most importantly, its ability to deliver the planned benefits. This analysis provides the necessary information for the program manager and governance body to make an informed decision on how to proceed, which may include updating the program roadmap and other subsidiary plans.
A. Negotiating to avoid a compliance audit is unprofessional and ignores a critical business and legal requirement mandated by the CEO.
B. De-scoping a core capability is a major strategic decision and a premature reaction that should only be considered after a comprehensive impact analysis.
C. Accepting the risk and continuing as planned is negligent, as it ignores a direct executive mandate and a new compliance requirement, exposing the organization to significant legal and financial risk.
1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 3.4, Program Change Management. This section details the process for managing changes, which begins with identifying and then assessing the impact of a change before any other action is taken. The CEO's request is a form of change request.
2. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 3.1.4.2, Monitoring and Controlling the Program Environment. This section states that program managers are responsible for monitoring external environmental factors (such as new regulations) and "assessing their impact on the program's business case, objectives, and benefits."
3. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Figure 3-13, Program Change Management. This figure illustrates the standard process flow, which clearly shows that after a change is identified, the next step is to "Assess Impact of Change" before it is approved, rejected, or deferred.
Keep practicing
Take the free PGMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PGMP practice questions
- Question 1You are the program manager of the NHQ Program. You will need to initiate six projects fo…
- Question 2All of the following are resources that you will need to monitor and control in a program…
- Question 3A company is evaluating the implementation of enterprise resource planning (ERP) software…
- Question 4The program manager defines the program objectives, requirements, and develops a high-lev…
- Question 5Which of the following represents the duration of activities against a calendar?
- Question 6During the selection of source process, you assign certain points towards various categor…