PGMP practice question 10 of 35
is the degree to which a set of inherent characteristics fulfills requirements.
Full set: 452 questionsThe phrase "the degree to which a set of inherent characteristics fulfills requirements" is the official definition of quality according to the Project Management Institute (PMI) and the International Organization for Standardization (ISO). In program management, quality is not about perfection but about ensuring that the program's outputs and outcomes meet the specified requirements and are fit for their intended purpose, thereby contributing to the realization of program benefits. The program manager establishes the overarching quality policy and framework to be applied across all component projects.
A. Scope defines the boundaries and the work to be performed, not the measure of how well that work meets its requirements.
B. A project phase is a collection of logically related activities, representing a division of the project lifecycle, not a measure of fulfillment.
C. A regulation is a mandatory requirement imposed by a governmental body; it is a type of requirement, not the degree of fulfillment.
1. Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section X3
Glossary
p. 213. Newtown Square
PA: Project Management Institute.
2. Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (6th ed.). Section 8
Project Quality Management
p. 274; and Appendix X1
Glossary
p. 718. Newtown Square
PA: Project Management Institute.
3. International Organization for Standardization. (2015). ISO 9000:2015: Quality management systems — Fundamentals and vocabulary. Section 3.6.2. Geneva
Switzerland: ISO.
Keep practicing
Take the free PGMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PGMP practice questions
- Question 1You are the program manager of the NHQ Program. You will need to initiate six projects fo…
- Question 2All of the following are resources that you will need to monitor and control in a program…
- Question 3A company is evaluating the implementation of enterprise resource planning (ERP) software…
- Question 4The program manager defines the program objectives, requirements, and develops a high-lev…
- Question 5Which of the following represents the duration of activities against a calendar?
- Question 6During the selection of source process, you assign certain points towards various categor…