A team member does not understand what the project risks are or the impact that they could have. How should an agile leader communicate risks in a way that the team will understand?
Full set: 482 questionsAgile teams use simple, highly visible tools to communicate information. A risk burndown chart is a visual radiator that shows the cumulative project risk exposure over time. It effectively communicates the number and magnitude of risks and tracks the team's progress in mitigating them. This transparency helps all team members, including the one who is unclear, to quickly grasp the current risk landscape and the impact of mitigation efforts without needing to read a complex document.
A. A RACI chart (often mistyped as RAG) defines roles and responsibilities for tasks; it does not explain the nature or impact of project risks.
B. A Gantt chart is a traditional scheduling tool. While it can include buffers, it does not explicitly communicate or visualize specific project risks and their impacts.
C. A communications management plan is a formal document outlining strategy; it is not the tool used for the direct communication and visualization of risks to the team.
1. Project Management Institute. (2017). Agile Practice Guide. Section 5.5.2, Agile Risk Management, p. 93. The guide lists "Risk burndown charts" as a tool for tracking and communicating risks.
2. Schuh, P. (2005). Integrating Agile Development in the Real World. Cengage Learning. This text discusses the use of visual charts, including risk burndown charts, to provide transparency and facilitate team understanding of project status and impediments.
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …