PMI-ACP practice question 22 of 35
At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity. How should the project team address this issue?
Full set: 482 questionsPair programming partners an inexperienced engineer with a skilled teammate, immediately raising quality, transferring knowledge, and improving velocity without reshuffling backlog or lowering story complexity. (PMI APG §4.6; Williams et al. 2000)
B. Re-prioritizing backlog does not solve the skill gap.
C. Re-estimation masks the capability issue instead of fixing it.
D. Assigning easier tasks limits learning and throttles throughput.
1. PMI. Agile Practice Guide, 2017, §4.6 “Technical Practices—Pair Programming,” p. 57.
2. Williams, L. et al. “Strengthening the Case for Pair Programming.” IEEE Software, 2000, p. 20. DOI:10.1109/52.877930
3. Stanford CS-E180 “Extreme Programming,” slide 14 (Knowledge sharing via pairing).
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …