PMI-ACP practice question 27 of 35
Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item. Which of the following should the agile project manager do?
Full set: 482 questionsThe core issue is a lack of transparency regarding work status, which is a key agile principle. An information radiator is a large, highly visible display that provides real-time information to anyone who is interested, without requiring them to ask. Examples include physical or digital Kanban boards, task boards, or dashboards showing work in progress, assignments, and status. This "pull" system allows stakeholders to get updates passively, fostering transparency and trust while minimizing interruptions to the team.
B. Sending updates on request is a reactive, "push" system that creates administrative overhead and is less efficient than a centralized, visible radiator.
C. Scrum meetings, particularly the Daily Scrum, are for the development team to coordinate their work, not for stakeholder status reporting.
D. Instructing the team to focus only on their own work is counterproductive and reduces transparency, collaboration, and collective ownership, worsening the problem.
1. Project Management Institute. (2017). Agile Practice Guide. Section 5.3.1, Information Radiators, p. 60. ("To share information with the team and stakeholders, agile teams use information radiators... The purpose is to have a visible, significant display that provides information without the viewer having to ask.").
2. Cockburn, A. (2001). Agile Software Development. Chapter 1, "A Cooperative Game of Invention and Communication." (Cockburn coined the term "information radiator" and describes its importance for osmotic communication).
3. Stray, V., & Moe, N. B. (2020). Understanding coordination in global software engineering: A mixed-methods study on the use of meetings and information radiators. IET Software, 14(4), 351-359. https://doi.org/10.1049/iet-sen.2019.0151 (Provides academic research on the effectiveness of information radiators for team and stakeholder coordination).
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …