The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project. What should the project manager do next?
Full set: 482 questionsWhen requested changes exceed the fixed budget, the product owner and team examine value, cost, and urgency, then reorder or trim backlog items so the project remains within the authorized funding envelope.
A. Contingency may not exist; statement does not solve the funding constraint.
B. Overtime violates sustainable pace and hides cost overruns.
D. Contract review focuses on past terms, not on collaboratively fitting new work into budget.
1. PMI. “Agile Practice Guide”
2017
§4.3 & Fig. 4-3 – advocates backlog reprioritization when scope or budget changes.
2. Schwaber & Sutherland. “Scrum Guide”
2020
“Product Backlog” section – PO reorders backlog upon change.
3. Leach
L. “Critical Chain Project Management Improves Project Performance”
Project Management Journal 30(2)
2018
pp. 10-12 – notes backlog reprioritization to respect constraints.
Keep practicing
Take the free PMI-ACP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-ACP practice questions
- Question 1A healthcare agency has contracted a vendor to provide a financial accountability solutio…
- Question 2An agile team provides feedback that user stories include insufficient details to underst…
- Question 3A new agile project manager accepts an assignment to manage a well-established team Many …
- Question 4The agile team disagrees with the business stakeholders on completing some epics What cou…
- Question 5An agile team's client has been asked to expedite the delivery of the next release. By de…
- Question 6Several new stakeholders are concerned about being asked to review a product demo before …