PMI-CAPM practice question 14 of 35

For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B…

Choose your answer, then check it against the explanation.

For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?

Answer options
Question 14 of 35

Keep practicing

Take the free PMI-CAPM practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-CAPM practice questions

Scroll to Top