PMI-DASSM practice question 9 of 25
What goal diagrams should a team select first?
Full set: 193 questionsDisciplined Agile’s goal diagrams are intended to help teams select the process decisions that fit their unique situation. The framework explicitly instructs teams to start with the goal(s) that are most relevant to their immediate context (e.g., current phase, life-cycle, and challenges). This maximises practical value and avoids unnecessary analysis of goals that do not presently apply.
A. Lack of experience alone is not a selection criterion; relevance takes precedence.
B. Customer/stakeholder choices may overlook internal process needs; DA is team-driven.
C. “Easiest” goals may be irrelevant and provide little benefit; context alignment is key.
1. Ambler, S.W. & Lines, M. “Choose Your WoW!”, PMI Press, 2020, p. 17 (How to Use Goal Diagrams – start with those relevant to your context).
2. University of Calgary, Software Engineering 699 Lecture Notes (2021) – Disciplined Agile Goal-Driven Approach, slide 12 (“Select the goal most germane to your situation”).
Keep practicing
Take the free PMI-DASSM practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-DASSM practice questions
- Question 1DA guidelines includes using design thinking. The primary advantage of design thinking is…
- Question 2Why is the coordination meeting important for a project team?
- Question 4What is the role of the product owner?
- Question 5During which iterative ceremony should someone obtain feedback?
- Question 6What are the three phases common across project life cycles?
- Question 7A scrum master needs to set up a team for a long-term project that has the potential for …