PMI-PBA practice question 28 of 30
A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?
Full set: 200 questionsFormal signoff is recommended in situations characterized by high risk, significant consequences of failure, or stringent regulatory/contractual obligations. A scenario where errors could impact the company's financial solvency represents the highest level of business risk. In such cases, formal signoff provides a documented record of acceptance from authorized stakeholders, ensuring accountability, confirming that the solution meets critical needs, and providing a legal and procedural safeguard before proceeding. This formality is crucial for mitigating severe potential negative impacts.
A. An unregulated industry reduces the need for formal oversight and signoff, making this a reason against formal signoff.
B. A project with a small, contained impact has lower risk, suggesting that a less formal acceptance process would be sufficient.
D. Iterative life cycles often rely on continuous, informal acceptance of increments at the end of each iteration, rather than a single, formal signoff at the end.
1. Project Management Institute. (2017). The PMI Guide to Business Analysis. Section 7.3, Obtain Solution/Requirements Acceptance. p. 237. This section notes that the acceptance process is influenced by organizational policies, and high-risk or regulated projects typically require more formal acceptance procedures.
2. Project Management Institute. (2017). The PMI Guide to Business Analysis. Section 7.3.1.2, Organizational Process Assets. p. 238. It mentions that policies for approvals and signoffs are key inputs, implying that high-impact projects (e.g., those affecting financial solvency) would have stringent policies.
Keep practicing
Take the free PMI-PBA practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-PBA practice questions
- Question 1A project team has completed the system use cases along with accompanying screen mockups.…
- Question 2Which of the following tools will help facilitate the decision-making process when stakeh…
- Question 3Which of the following is the best approach to enable developers and product owners to be…
- Question 4A business analyst is planning the business analysis activities for a new payroll project…
- Question 5What should a business analyst do after discovering that two solution requirements confli…
- Question 6Which of the following techniques is used to identify ambiguous or unverifiable requireme…
