PMI-PBA practice question 29 of 30

A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:

Full set: 200 questions
Answer options
A: requirements gathering workshops with the stakeholders. Correct answer
B: requirements acceptance with the customer.
C: requirements validation with the testers.
D: requirements sign-off with the customer.
Correct Answer:
A. requirements gathering workshops with the stakeholders.
Explanation

When development begins before requirements are finalized, it creates significant risk. The business analyst's immediate priority is to regain control by aligning stakeholders and the development team. Facilitating a requirements gathering workshop is the most effective first step. This collaborative approach allows for the rapid finalization of the incomplete requirements, clarifies ambiguities, and establishes a shared understanding. This creates a stable baseline from which development can proceed in a controlled manner, preventing rework and ensuring the solution meets business needs.

Why Incorrect

B. Requirements acceptance is a formal step that occurs much later, typically during user acceptance testing, to confirm the solution meets the criteria.
C. Requirements validation with testers happens after requirements are defined and baselined, to ensure they are clear, consistent, and testable.
D. Requirements sign-off is the goal, but it cannot be the first step if the documentation is incomplete, as stated in the scenario.

References

- Project Management Institute. (2017). Business Analysis for Practitioners: A Practice Guide. Section 5.3.2.2, p. 82. This section describes workshops as a key collaborative technique for eliciting and refining requirements with stakeholders.

- Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Section 5.2.2.3, p. 143. Describes facilitation and workshops as key tools for collecting requirements.