PMI-PBA practice question 30 of 30

The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap. Which technique should the business analyst have followed to ensure consensus?

Full set: 200 questions
Answer options
A: The business analyst should have performed a complete review of each requirement with one of the stakeholders’ peers before the meeting.
B: The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting. Correct answer
C: The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.
D: The business analyst should have invited the key stakeholders to the meeting.
Correct Answer:
B. The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.
Explanation

The failure to achieve sign-off due to a "communication gap" indicates that the stakeholders were not properly aligned before the formal review meeting. The best practice to prevent this is to engage in preliminary reviews and discussions with the key stakeholders prior to the formal sign-off event. By reviewing the requirements documentation with them individually or in small groups beforehand, the business analyst can address questions, resolve issues, and build consensus. This ensures that the formal meeting is merely a final confirmation of an agreement that has already been reached.

Why Incorrect

A. Reviewing with stakeholders' peers is insufficient, as peers do not have the authority to provide the necessary sign-off for the baseline.
C. Focusing only on the project sponsor neglects other key stakeholders whose agreement is also critical for establishing a consensus-based baseline.
D. The stakeholders were already present at the meeting; their attendance was not the issue, but rather their lack of prior alignment and readiness.

References

- Project Management Institute. (2017). The PMI Guide to Business Analysis. Section 5.6, Obtain Requirements Sign-off. This section emphasizes that obtaining sign-off is a process of gaining agreement and endorsement, which requires proactive communication and consensus-building activities before a formal decision point.

- Project Management Institute. (2015). Business Analysis for Practitioners: A Practice Guide. Section 4.4, Conduct Elicitation. This guide highlights the importance of continuous stakeholder communication and feedback loops to ensure shared understanding and prevent surprises during formal reviews.