PMI-PBA practice question 8 of 30
The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?
Full set: 200 questionsThe requirements baseline is the formally approved set of requirements that the project team has committed to delivering. It serves as the definitive source for what is in scope for a particular release or for the project as a whole. Providing this document to the project sponsor directly and authoritatively answers the question of which requirements will be implemented. Any changes to this baseline must go through a formal change control process.
A. A requirements traceability matrix shows relationships between requirements and other artifacts but does not, by itself, represent the final, approved scope.
C. The requirements management plan describes the process for managing requirements; it does not list the actual requirements to be implemented.
D. A requirements impact analysis is a study conducted to evaluate the effects of a proposed change, not a document listing the full scope.
1. Project Management Institute. (2017). The PMI Guide to Business Analysis. Section 4.4.2.1, "Requirements Baseline," p. 122. Defines the baseline as the approved requirements that form the basis for project work.
2. Project Management Institute. (2015). Business Analysis for Practitioners: A Practice Guide. Section 5.6, "Establish the Requirements Baseline," p. 80. States that the baseline is the agreed-upon requirements that will be used to manage the project execution.
Keep practicing
Take the free PMI-PBA practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-PBA practice questions
- Question 1A project team has completed the system use cases along with accompanying screen mockups.…
- Question 2Which of the following tools will help facilitate the decision-making process when stakeh…
- Question 3Which of the following is the best approach to enable developers and product owners to be…
- Question 4A business analyst is planning the business analysis activities for a new payroll project…
- Question 5What should a business analyst do after discovering that two solution requirements confli…
- Question 6Which of the following techniques is used to identify ambiguous or unverifiable requireme…
