PMI-RMP practice question 17 of 35
As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary…
Choose your answer, then check it against the explanation.
As per the risk analysis process carried out for a project, two risks are registered. The probability risk
A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will
occur is 60% and its monetary impact to the project is US$20,000.
What is the total contingency budget that should be created?
Question 17 of 35
Keep practicing
Take the free PMI-RMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMI-RMP practice questions
- Question 1Business rhythm can fluctuate greatly between different industries and vary between compa…
- Question 2A risk manager for a hospital extension project is leading a project team in developing a…
- Question 3A project lihat was in the execution phase for the last six months was put on hold and wa…
- Question 4Which statement describes the risk portrayed on the risk matrix heat map below?
- Question 5Stakeholder deliverable reviews will start soon and additional work is expected to resolv…
- Question 6A risk management professional is currently facilitating the risk planning process with t…
