PMI-RMP practice question 17 of 35

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary…

Choose your answer, then check it against the explanation.

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000. What is the total contingency budget that should be created?
Answer options
Question 17 of 35

Keep practicing

Take the free PMI-RMP practice test

Ten exam-style questions with answers and explanations, plus the exam facts and study guides.

Start the free practice test

More questions

Other PMI-RMP practice questions

Scroll to Top