A project team is working across different time zones and all team members are unable to attend the daily coordination meetings at the same time. The tasks are split across teams working independently in different regions; however, there are task dependencies between the two teams. What should the team lead do?
Full set: 230 questionsDomain People
In distributed projects with significant time zone differences where synchronous daily meetings are impossible, the team lead should facilitate robust asynchronous communication. By ensuring teams create, update, and access shared project artifacts (such as Kanban boards, dependency logs, or shared digital workspaces), team members can track progress and manage cross-regional dependencies effectively. This approach leverages "information radiators" to provide continuous transparency and alignment without requiring simultaneous meeting attendance. It ensures that critical dependency information is always available, thereby supporting a sustainable work pace and adhering to PMI’s best practices for managing virtual and distributed teams.
A. Forcing attendance regardless of time zones leads to team burnout, violates the agile principle of maintaining a sustainable pace, and reduces overall morale.
C. Scheduling additional meetings adds administrative overhead and does not resolve the fundamental logistical issue of incompatible time zones for daily, routine coordination.
D. Reassigning tasks based solely on time zones ignores individual resource skill sets, limits cross-functional team collaboration, and fails to address the root communication challenge.
1. Project Management Institute (PMI). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. (2021). Section 2.2 (Team Performance Domain - High-Performing Project Teams) and Section 2.7 (Measurement Performance Domain - Information Radiators).
2. Project Management Institute (PMI). Agile Practice Guide. (2017). Section 4.3.2 (Distributed Teams). This section explicitly discusses the necessity of using shared workspaces, information radiators, and asynchronous communication tools when managing teams across disparate time zones.
3. Project Management Institute (PMI). PMBOK® Guide – Sixth Edition. (2017). Section 9.4 (Develop Team - Virtual Teams), detailing the importance of shared communication technology and artifacts to bridge geographical and temporal gaps.
Keep practicing
Take the free PMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMP practice questions
- Question 1The project manager is preparing for the kickoff meeting of a project that follows a 'pla…
- Question 2Health Records Modernization at Hospital Case Study A project manager led a health record…
- Question 4A project manager is leading a project focused on developing a machine learning platform.…
- Question 5A project manager is leading an iterative project to develop a very innovative product. H…
- Question 6A team is using a predictive model to determine possible cost overrun scenarios for a dis…
- Question 7During the execution phase of a major infrastructure project, your team uncovers a signif…