During the execution of a project, the product manager receives a new product feature request from the organization's highest revenue-generating client. The team estimates the work will take three days. What should the project manager do?
Full set: 230 questionsDomain Process
In Agile methodologies, active sprints are timeboxed and their scope is protected to maintain team focus and achieve the Sprint Goal. When a new feature request is received, even from a highly valuable client, it must be added to the Product Backlog rather than disrupting the current iteration. The Product Owner prioritizes this new item based on its business value. The project manager (or Scrum Master) should facilitate the team's analysis of this request during backlog refinement. This allows the team to properly evaluate the three-day estimate and determine if the feature can be incorporated into the next sprint during the subsequent Sprint Planning event, ensuring adaptability without compromising current commitments.
A: Starting a new sprint immediately aborts or disrupts the current timeboxed iteration, violating Agile principles that protect the team's focus on the committed Sprint Goal. C: Fast-tracking is a predictive schedule compression technique. In Agile, injecting new scope into an active sprint is generally prohibited as it endangers the agreed-upon Sprint Goal. D: Running parallel sprints for a single team destroys focus, introduces severe context-switching penalties, and violates the fundamental Agile practice of working in single, sequential timeboxes.
1. Project Management Institute. (2017). Agile Practice Guide. Section 5.2.1 (Backlog Preparation) and Section 5.2.5 (Execution Practices)
pp. 58
61. (Details how new requests are placed in the backlog for future iteration planning).
2. Schwaber
K.
& Sutherland
J. (2020). The Scrum Guide. Section: The Sprint
p. 7. (States explicitly that during a Sprint
"No changes are made that would endanger the Sprint Goal").
3. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. Section 2.8.2 (Adaptability and Resiliency)
p. 122. (Discusses responding to change through structured reprioritization rather than immediate disruption).
Keep practicing
Take the free PMP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PMP practice questions
- Question 1The project manager is preparing for the kickoff meeting of a project that follows a 'pla…
- Question 2Health Records Modernization at Hospital Case Study A project manager led a health record…
- Question 4A project manager is leading a project focused on developing a machine learning platform.…
- Question 5A project manager is leading an iterative project to develop a very innovative product. H…
- Question 6A team is using a predictive model to determine possible cost overrun scenarios for a dis…
- Question 7During the execution phase of a major infrastructure project, your team uncovers a signif…