All of the following are true regarding Communications Planning except for which one?

Full set: 650 questions
Answer options
A: Communications requirements analysis, communications technology, and PMIS are tools and techniques of this process. Correct answer
B: It's the only output of the Communications Planning process.
C: It's tightly linked with enterprise environmental factors and organizational influences, and lessons learned and historical information are two inputs that should get a lot of attention during this process.
D: It should be completed as early in the project phases as possible.
Correct Answer:
A. Communications requirements analysis, communications technology, and PMIS are tools and techniques of this process.
Explanation

Communications requirements analysis and communications technology are the tools and techniques of the Communications Planning process.