Which of the following can be used to track the requirements throughout the project life cycle?

Full set: 650 questions
Answer options
A: Requirements traceability matrix Correct answer
B: Scope management plan
C: Project charter
D: Work breakdown structure
Correct Answer:
A. Requirements traceability matrix