PPM-001 practice question 28 of 35

Which of the following is a tool or technique of the Collect Requirements process?

Full set: 650 questions
Answer options
A: Group decision making techniques Correct answer
B: Project management information system
C: Alternative identification
D: Communication requirement analysis
Correct Answer:
A. Group decision making techniques