[Measure and Improve Deployment Management] An organization has an objective to create and use deployment approaches that would fit the needs of the organization and the context. How should the organization assess if this objective is achieved?
Full set: 140 questionsThe objective is to determine if deployment approaches "fit the needs of the organization and the context." This is a measure of effectiveness and value, which is best assessed through stakeholder feedback. Asking stakeholders about their satisfaction with deployment lead times directly measures whether the chosen deployment methods are meeting their expectations and business needs. High satisfaction indicates a good fit, while low satisfaction signals a mismatch between the approach and the context, prompting a review and improvement.
A: Deployment backlog throughput is a measure of efficiency (how much is done), not effectiveness (if the right thing is done in the right way). C: This measures compliance with policies. A deployment can be 100% compliant with a policy that is itself a poor fit for the organization's needs. D: Adherence to schedules measures predictability. A team can adhere perfectly to a schedule that is too slow or delivers at the wrong time for stakeholders.
ITIL® 4 Practitioner: Deployment Management. (2020). Axelos. Section 4.4, "Practice success factors and metrics," links metrics to practice success factors (PSFs). PSF 1, "Deployment of new and changed services according to the agreed models," is best measured by stakeholder satisfaction.
ITIL® 4: Drive Stakeholder Value. (2020). Axelos. Section 4.3.3, "Measuring stakeholder experience," emphasizes that direct feedback and satisfaction metrics are key to understanding if value is being co-created successfully.
Keep practicing
Take the free PRACTITIONER-DEPLOYMENT-MANAGEMENT practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRACTITIONER-DEPLOYMENT-MANAGEMENT practice questions
- Question 1What is the primary purpose of the staging environment in the deployment process?
- Question 2Which of the following is a key consideration when effectively removing a service from a …
- Question 3[Apply Deployment Management Processes] An organization is deploying new software and new…
- Question 4What is a vital metric to monitor post-deployment to ensure ongoing service effectiveness?
- Question 5[Engage with Stakeholders and Suppliers] Which is NOT an example of how an organization s…
- Question 6What approach should be taken when measuring the effectiveness of service deployments in …