PRINCE2-FOUNDATION practice question 30 of 35

How do issue management and change control relate to each other?

Full set: 478 questions
Answer options
A: Change control and Issue management are separate processes
B: Issue management is part of change control
C: change control is part of issue management Correct answer
D: issue management and change control are identical
Correct Answer:
C. change control is part of issue management
Explanation

In PRINCE2, change control is a subset of issue management. The method uses a single, unified 'issue and change control procedure' to manage all types of issues. An 'issue' is defined as any relevant event that was not planned and requires management action. There are three types of issues: requests for change, off-specifications, and problems/concerns. Therefore, the procedure for controlling changes is an integral part of the broader procedure for managing all issues.

Why Incorrect

A. They are not separate; they are managed through a single, integrated procedure called the 'issue and change control procedure'.
B. This inverts the relationship. Change control is a specific application of the broader issue management framework in PRINCE2.
D. They are not identical because issue management also covers off-specifications and problems/concerns, not just requests for change.

References

- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Section 10.3.1, "Issue", p. 118.

- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Section 10.4, "Issue and change control procedure", p. 120.

- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Figure 10.1, "Relationship between baselines, issues, and changes", p. 117.