PRINCE2-FOUNDATION practice question 30 of 35
How do issue management and change control relate to each other?
Full set: 478 questionsIn PRINCE2, change control is a subset of issue management. The method uses a single, unified 'issue and change control procedure' to manage all types of issues. An 'issue' is defined as any relevant event that was not planned and requires management action. There are three types of issues: requests for change, off-specifications, and problems/concerns. Therefore, the procedure for controlling changes is an integral part of the broader procedure for managing all issues.
A. They are not separate; they are managed through a single, integrated procedure called the 'issue and change control procedure'.
B. This inverts the relationship. Change control is a specific application of the broader issue management framework in PRINCE2.
D. They are not identical because issue management also covers off-specifications and problems/concerns, not just requests for change.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Section 10.3.1, "Issue", p. 118.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Section 10.4, "Issue and change control procedure", p. 120.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Figure 10.1, "Relationship between baselines, issues, and changes", p. 117.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?