PRINCE2-FOUNDATION practice question 29 of 35
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
Full set: 478 questionsThe Progress theme and its control mechanisms, such as setting tolerances and 'managing by exception', are fundamental to PRINCE2 and apply to all four levels of the project management team. Corporate or programme management controls the project as a whole. The project board controls progress at the management stage level. The project manager exerts day-to-day control over the stage and Work Packages. The team manager controls the execution of a Work Package. Each level uses progress information to monitor performance and control deviations within their delegated authority.
A. This is incorrect because the project board and project manager also use progress controls extensively to manage the project.
B. This is incorrect because the project manager and corporate/programme management also have distinct roles in controlling progress.
C. This is incorrect because the project board and team managers are also integral to the progress control mechanisms.
AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). Chapter 10, The PRINCE2 themes: Progress, Section 10.1, p. 111.
AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). Chapter 10, The PRINCE2 themes: Progress, Section 10.2, p. 112.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?
