PRINCE2-FOUNDATION practice question 29 of 35

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

Full set: 478 questions
Answer options
A: Only corporate or programme management
B: Only the Project Board
C: Only the Project Manager
D: All levels of management Correct answer
Correct Answer:
D. All levels of management
Explanation

The Progress theme and its control mechanisms, such as setting tolerances and 'managing by exception', are fundamental to PRINCE2 and apply to all four levels of the project management team. Corporate or programme management controls the project as a whole. The project board controls progress at the management stage level. The project manager exerts day-to-day control over the stage and Work Packages. The team manager controls the execution of a Work Package. Each level uses progress information to monitor performance and control deviations within their delegated authority.

Why Incorrect

A. This is incorrect because the project board and project manager also use progress controls extensively to manage the project.
B. This is incorrect because the project manager and corporate/programme management also have distinct roles in controlling progress.
C. This is incorrect because the project board and team managers are also integral to the progress control mechanisms.

References

AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). Chapter 10, The PRINCE2 themes: Progress, Section 10.1, p. 111.

AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). Chapter 10, The PRINCE2 themes: Progress, Section 10.2, p. 112.