PRINCE2-FOUNDATION practice question 28 of 35
Identify the missing word(s) in the following sentence. The 'controlling a stage' process is used to manage and control each [ ? ] of a project.
Full set: 478 questionsThe 'controlling a stage' process describes the work of the project manager in handling the day-to-day management of a delivery stage. Its purpose is to ensure the stage remains within its agreed tolerances. The project manager assigns work to be done, monitors this work, deals with issues and risks, and reports progress to the project board. This process is repeated for every delivery stage in the project, forming the core of the project manager's control activities during project execution.
A. A 'delivery step' is a more granular term for an activity or work package, which is managed within a stage, not what the entire process controls.
B. A 'benefit' is a measurable improvement resulting from an outcome. Benefits are realized after the project, not managed via the 'controlling a stage' process.
D. A 'team plan' is an optional plan created by a team manager to detail how a work package will be executed. The process controls the entire stage, not just one team plan.
1. AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Chapter 19, "Controlling a stage process," Figure 19.1, shows the context of the process.
2. AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Section 19.1, "Purpose," states the purpose is to manage and control the project manager's work during a delivery stage.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?