PRINCE2-FOUNDATION practice question 28 of 35

Identify the missing word(s) in the following sentence. The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

Full set: 478 questions
Answer options
A: delivery step
B: benefit
C: delivery stage Correct answer
D: team plan
Correct Answer:
C. delivery stage
Explanation

The 'controlling a stage' process describes the work of the project manager in handling the day-to-day management of a delivery stage. Its purpose is to ensure the stage remains within its agreed tolerances. The project manager assigns work to be done, monitors this work, deals with issues and risks, and reports progress to the project board. This process is repeated for every delivery stage in the project, forming the core of the project manager's control activities during project execution.

Why Incorrect

A. A 'delivery step' is a more granular term for an activity or work package, which is managed within a stage, not what the entire process controls.
B. A 'benefit' is a measurable improvement resulting from an outcome. Benefits are realized after the project, not managed via the 'controlling a stage' process.
D. A 'team plan' is an optional plan created by a team manager to detail how a work package will be executed. The process controls the entire stage, not just one team plan.

References

1. AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Chapter 19, "Controlling a stage process," Figure 19.1, shows the context of the process.

2. AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Section 19.1, "Purpose," states the purpose is to manage and control the project manager's work during a delivery stage.