PRINCE2-FOUNDATION practice question 8 of 35
How does the ‘managing product delivery’ process achieve its purpose?
Full set: 478 questionsThe purpose of the ‘managing product delivery’ process is to control the link between the project manager and the team manager. This is achieved by the project manager issuing formal requirements for the work in a work package. The team manager then accepts this work package, formally agreeing to the requirements for how the work should be undertaken, including constraints, quality criteria, and reporting arrangements, before executing the work and delivering the products.
B. Highlight reports are created by the project manager for the project board during the ‘controlling a stage’ process, not by the team manager in ‘managing product delivery’.
C. The team manager, not the project manager, is responsible for producing a team plan if one is required. The project manager monitors progress against the stage plan.
D. The project manager escalates issues and risks that are forecast to exceed stage tolerance to the project board. This occurs within the ‘controlling a stage’ process.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Chapter 19, "Managing product delivery process," p. 223.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Figure 19.1, "Managing product delivery context," p. 224.
- AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Section 17.4.4, "Report highlights," p. 208.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?