PRINCE2-FOUNDATION practice question 26 of 35

How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?

Full set: 478 questions
Answer options
A: The work packages are defined by the team manager and supported by a team plan
B: the work packages provided by the project manager are agreed by the team manager Correct answer
C: The team plans are checked by project assurance against the work packages
D: The stage plan covering the work packages is created with input from the team manager
Correct Answer:
B. the work packages provided by the project manager are agreed by the team manager
Explanation

The 'managing product delivery' process governs the interface between the project manager and the team manager. A central activity within this process is 'accept a work package'. During this activity, the team manager formally agrees with the project manager that the work package's requirements, constraints, and tolerances are achievable. This formal agreement ensures the team manager's perspective is considered and that there is a shared understanding and commitment before work commences. It is the primary mechanism for ensuring the work package is realistic from the delivery team's viewpoint.

Why Incorrect

A. The project manager defines and authorizes the work package; the team manager accepts it and may then create a team plan.
C. Project assurance provides independent checks, but this is not the primary mechanism for incorporating the team manager's perspective into the work package itself.
D. The team manager may provide input to the stage plan, but this occurs in the 'managing a stage boundary' process, not 'managing product delivery'.

References

AXELOS, "Managing Successful Projects with PRINCE2 7th Edition" (2023), Chapter 16 Managing product delivery, Section 16.1 Purpose, p. 201.

AXELOS, "Managing Successful Projects with PRINCE2 7th Edition" (2023), Section 16.4.1 Accept a work package, p. 203. ("The team manager must agree with the project manager that they can produce the required products within the constraints.")