PRINCE2-FOUNDATION practice question 26 of 35
How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?
Full set: 478 questionsThe 'managing product delivery' process governs the interface between the project manager and the team manager. A central activity within this process is 'accept a work package'. During this activity, the team manager formally agrees with the project manager that the work package's requirements, constraints, and tolerances are achievable. This formal agreement ensures the team manager's perspective is considered and that there is a shared understanding and commitment before work commences. It is the primary mechanism for ensuring the work package is realistic from the delivery team's viewpoint.
A. The project manager defines and authorizes the work package; the team manager accepts it and may then create a team plan.
C. Project assurance provides independent checks, but this is not the primary mechanism for incorporating the team manager's perspective into the work package itself.
D. The team manager may provide input to the stage plan, but this occurs in the 'managing a stage boundary' process, not 'managing product delivery'.
AXELOS, "Managing Successful Projects with PRINCE2 7th Edition" (2023), Chapter 16 Managing product delivery, Section 16.1 Purpose, p. 201.
AXELOS, "Managing Successful Projects with PRINCE2 7th Edition" (2023), Section 16.4.1 Accept a work package, p. 203. ("The team manager must agree with the project manager that they can produce the required products within the constraints.")
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?