PRINCE2-FOUNDATION practice question 25 of 35

What product defines the reporting requirements between the Project Manager and Team Manager?

Full set: 478 questions
Answer options
A: Project Brief
B: Product Description
C: Team Plan
D: Work Package Correct answer
Correct Answer:
D. Work Package
Explanation

The Work Package is the management product used by the Project Manager to issue a set of instructions and information to a Team Manager or team members. It forms an agreement defining what is to be produced. A key component of the Work Package is the 'Reporting arrangements', which specifies the frequency and format of progress reporting required from the Team Manager to the Project Manager, ensuring clear communication and control during product delivery.

Why Incorrect

A. The Project Brief is an early document providing a high-level outline of the project; it does not contain detailed operational reporting requirements for teams.
B. A Product Description defines the characteristics and quality criteria of a single product, not the management and reporting process for creating it.
C. A Team Plan is an optional plan created by the Team Manager detailing how the Work Package objectives will be met; it is not the document that defines the requirements from the PM.

References

AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Appendix A, Section A.29, p. 388.