PRINCE2-FOUNDATION practice question 24 of 35
Which statement BEST describes how approved plans enable control?
Full set: 478 questionsApproved plans are a primary tool for control in PRINCE2. They establish baselines for the six performance targets, including scope. By clearly defining the products to be delivered, the plan sets the project's scope. This baseline is then used to monitor progress and identify any unapproved changes or additions, which is known as scope creep. The plan provides the formal basis against which requests for change are assessed, thereby enabling control over the project's scope.
A. This is only one aspect of control (quality); plans provide broader control over scope, time, and cost.
B. The business case, not the plan itself, is the primary document for considering business opportunities.
C. The benefits management approach defines how benefits are managed; plans focus on delivering the outputs that enable those benefits.
AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Section 10.1, "The purpose of the plans practice," p. 118.
AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Section 10.2, "Plans and the PRINCE2 principles," p. 119.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?