PRINCE2-FOUNDATION practice question 24 of 35

Which statement BEST describes how approved plans enable control?

Full set: 478 questions
Answer options
A: By defining the quality specifications of individual products in product descriptions
B: By enabling the controlled consideration of business opportunities
C: By defining the benefits that need to be realized through the benefits management approach
D: By defining what is within the approved project scope to avoid scope creep Correct answer
Correct Answer:
D. By defining what is within the approved project scope to avoid scope creep
Explanation

Approved plans are a primary tool for control in PRINCE2. They establish baselines for the six performance targets, including scope. By clearly defining the products to be delivered, the plan sets the project's scope. This baseline is then used to monitor progress and identify any unapproved changes or additions, which is known as scope creep. The plan provides the formal basis against which requests for change are assessed, thereby enabling control over the project's scope.

Why Incorrect

A. This is only one aspect of control (quality); plans provide broader control over scope, time, and cost.
B. The business case, not the plan itself, is the primary document for considering business opportunities.
C. The benefits management approach defines how benefits are managed; plans focus on delivering the outputs that enable those benefits.

References

AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Section 10.1, "The purpose of the plans practice," p. 118.

AXELOS. (2023). Managing Successful Projects with PRINCE2 7. PeopleCert. Section 10.2, "Plans and the PRINCE2 principles," p. 119.

Scroll to Top