PRINCE2-FOUNDATION practice question 23 of 35

As a minimum requirement for applying the risk theme, what must specifically be assessed?

Full set: 478 questions
Answer options
A: Whether a risk may cause the project to exceed its cost tolerance
B: Whether a risk may affect the project-level quality tolerances
C: Whether a risk may impact the underlying technical assumptions
D: Whether a risk may alter the project's business justification Correct answer
Correct Answer:
D. Whether a risk may alter the project's business justification
Explanation

The primary purpose of the risk theme is to manage uncertainty to protect the project's viability. The ultimate measure of a risk's significance is its potential impact on the project's business justification. While risks are assessed against objectives like cost and time, these are important because they underpin the business case. Therefore, a minimum requirement is to assess whether a risk, or the aggregate of all risks, threatens the continued business justification for the project.

Why Incorrect

A. Whether a risk may cause the project to exceed its cost tolerance: This is only one type of impact; risks can also affect time, quality, scope, benefits, and sustainability.
B. Whether a risk may affect the project-level quality tolerances: This is too specific and represents only one of the six performance objectives that a risk could impact.
C. Whether a risk may impact the underlying technical assumptions: This is a potential cause or source of risk, not the ultimate impact on the project's objectives that must be assessed.

References

AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Chapter 10, Section 10.1, p. 113; Chapter 10, Section 10.4, p. 126.