PRINCE2-FOUNDATION practice question 22 of 35
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
Full set: 478 questionsThe purpose of the progress theme is to establish mechanisms to monitor and compare actual achievements against those planned, provide a forecast for the project objectives, and control any unacceptable deviations. It provides the framework for management control by defining tolerances at the project, stage, and work package levels. This allows each management level to monitor progress and escalate issues when tolerances are forecast to be exceeded, ensuring ongoing control throughout the project lifecycle.
B. The change theme provides a systematic approach to assessing and controlling issues, not the overall mechanisms for monitoring project progress.
C. The organization theme defines the project management team structure, roles, and responsibilities, not the control mechanisms they use.
D. The quality theme defines and implements the means by which the project will verify that products are fit for purpose.
1. AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). PeopleCert. Chapter 11, "Progress," Section 11.1, "Purpose of the progress theme," explicitly states its purpose is to establish mechanisms for monitoring and control.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?