What does the communication management approach define? 1. How versions of products will be described on information sent to interested parties 2. How information should be sent to interested parties 3. How often information should be sent to interested parties 4. How the PRINCE2 roles will be combined during the project
Full set: 478 questionsThe communication management approach is a plan that defines the method and frequency of communication with parties both internal and external to the project. It answers questions about what information needs to be communicated, to whom, how (the method of communication), and how often. Therefore, it explicitly defines how and how often information should be sent to interested parties (stakeholders). This ensures that communications are planned and controlled, rather than being ad-hoc.
1. How versions of products will be described is part of the change and configuration management approach, which deals with product identification and version control.
4. How PRINCE2 roles will be combined is an aspect of tailoring the project management team structure, which is documented in the project initiation documentation (PID).
AXELOS. (2023). Managing Successful Projects with PRINCE2 7. TSO (The Stationery Office). Section 5.4.1, "Communication management approach," p. 51. It states the approach should describe "the method of communication (such as meetings, emails, and workshops) and the frequency of communication."
AXELOS. (2023). Managing Successful Projects with PRINCE2 7. TSO (The Stationery Office). Appendix A, "Management product: Communication management approach," p. 316.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?