PRINCE2-FOUNDATION practice question 14 of 35

What does the communication management approach define? 1. How versions of products will be described on information sent to interested parties 2. How information should be sent to interested parties 3. How often information should be sent to interested parties 4. How the PRINCE2 roles will be combined during the project

Full set: 478 questions
Answer options
A: 1 and 2
B: 2 and 3 Correct answer
C: 3 and 4
D: 1 and 4
Correct Answer:
B. 2 and 3
Explanation

The communication management approach is a plan that defines the method and frequency of communication with parties both internal and external to the project. It answers questions about what information needs to be communicated, to whom, how (the method of communication), and how often. Therefore, it explicitly defines how and how often information should be sent to interested parties (stakeholders). This ensures that communications are planned and controlled, rather than being ad-hoc.

Why Incorrect

1. How versions of products will be described is part of the change and configuration management approach, which deals with product identification and version control.
4. How PRINCE2 roles will be combined is an aspect of tailoring the project management team structure, which is documented in the project initiation documentation (PID).

References

AXELOS. (2023). Managing Successful Projects with PRINCE2 7. TSO (The Stationery Office). Section 5.4.1, "Communication management approach," p. 51. It states the approach should describe "the method of communication (such as meetings, emails, and workshops) and the frequency of communication."

AXELOS. (2023). Managing Successful Projects with PRINCE2 7. TSO (The Stationery Office). Appendix A, "Management product: Communication management approach," p. 316.