PRINCE2-FOUNDATION practice question 13 of 35
What is a description of a leadership activity within a project?
Full set: 478 questionsLeadership is about creating a vision and inspiring others to follow it. In a project context, this often involves looking outwards from the project to engage and influence stakeholders. Understanding and working with different departments outside the immediate project team is a key leadership activity, as it requires communication, negotiation, and building relationships to ensure wider organizational support and alignment for the project. The other options describe specific management tasks focused on planning and control.
B. Agreeing a work package with a tear manager to deliver products using specific tools: This is a defined management control activity within the 'controlling a stage' process.
C. Ensuring that a co-located project team uses the agreed communication methods: This is a management activity focused on monitoring and controlling adherence to an agreed plan.
D. Creating a stage plan and product descriptions for the products to be created in the next stage: This is a core management activity of planning, which occurs in the 'managing a stage boundary' process.
AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Section 4.4.2, "Leadership involves creating a vision and inspiring people to follow it... Management is more about directing or controlling people and resources according to established principles."
AXELOS. (2023). Managing Successful Projects with PRINCE2 (7th ed.). TSO (The Stationery Office). Table 4.1, which contrasts management (e.g., focus on systems, control, how and when) with leadership (e.g., focus on people, trust, what and why). Working with other departments aligns with the people and 'what/why' focus of leadership.
Keep practicing
Take the free PRINCE2-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PRINCE2-FOUNDATION practice questions
- Question 1How should effective issue management be applied When changing management products?
- Question 2Which is one of the six aspects of project performance to be managed?
- Question 3Which is a benefit of using PRINCE2?
- Question 4Which is an assumption about the PRINCE2 customer/supplier environment?
- Question 5What is an advantage of applying the 'manage by stages' principle?
- Question 6Which is a minimum requirement for applying the quality theme?