PROJECT-MANAGEMENT practice question 11 of 15
Near the end of a routine job site visit, the architect begins to assemble notes. The owner's representative then arrives on site unexpectedly. The…
Full set: 79 questionsThe scenario describes a meeting where outstanding issues were discussed and resolved. While a Meeting Record documents the discussion and decisions, an Action Item List is the specific project management tool used to translate those resolutions into concrete, trackable tasks. This list assigns responsibility for each task and sets a due date, ensuring that the agreements made during the impromptu meeting are formally implemented and not overlooked. Creating this list is a crucial step in maintaining accountability and project momentum following a decision-making meeting.
B. Field Observation Report: A Field Observation Report is used to document the progress and quality of the work observed during the site visit itself, not the specific outcomes of a meeting.
C. Email Message: An email is a method of communication or transmittal. The formal documentation (Meeting Record, Action Item List) would be attached to or summarized in an email, but the email is not the official record itself.
1. The American Institute of Architects. (2017). The Architect's Handbook of Professional Practice (15th ed.). John Wiley & Sons.
Section 9.4, Project Communications, "Meeting Reports" (p. 619): This section explicitly states that effective meeting reports should "list action items, the party responsible for each, and the date for completion." This directly supports the creation of an Action Item List as a standard follow-up to a meeting where resolutions are made.
2. The American Institute of Architects. (2018). AIA Document G711–2018, Architect’s Field Report.
Instructions, "Purpose": The document's purpose is defined for the architect "to record observations made at the site." This confirms that its function is distinct from documenting the resolutions and subsequent tasks arising from a project meeting.
3. Wentling, R. (2002). Planning for Effective Project Management. University of Illinois at Urbana-Champaign, National Center for Research in Vocational Education.
Section on "Conducting Project Meetings" (p. 18): This educational resource emphasizes that after a meeting, minutes should be distributed that include "a list of all decisions made and action items." This highlights the academic and professional best practice of separating and formalizing action items for clarity and tracking.
Keep practicing
Take the free PROJECT-MANAGEMENT practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PROJECT-MANAGEMENT practice questions
- Question 1Which of the following best describes a construction manager (CM) at risk?
- Question 2During the preparation of the construction documents, it was noted that the survey inaccu…
- Question 3According to ATA owner-architect agreements, who is responsible for the cost of evaluatin…
- Question 4During the bidding phase, what is the architect’s role regarding addenda?
- Question 5What is the architect’s role regarding shop drawings?
- Question 6Which four factors will most affect the choice of project delivery method? Check the four…