True or False: A Sprint can be canceled before the timebox ends.
Full set: 163 questionsCorrect Answer:
A. True
Explanation
A Sprint can be canceled if the Sprint Goal becomes obsolete, as stated in the Scrum Guide. This decision is made by the Product Owner, and it emphasizes Scrum's focus on delivering value.