PSD practice question 5 of 25
True or False: Stakeholders can be included in Product Backlog refinement.
Full set: 163 questionsCorrect Answer:
A. True
Explanation
Stakeholders may be included in Product Backlog refinement to provide clarity and additional information, helping the Scrum Team better understand the requirements and priorities.