PSM-1 practice question 35 of 35

How is management external to the Scrum Team involved in the Daily Scrum? (Choose the best Answer)

Full set: 298 questions
Answer options
A:

A. The Scrum Master speaks on their behalf.

B:

B. Managers are not required at the Daily Scrum.

Correct answer
C:

C. Management gives an update at the start of each Daily Scrum.

D:

D. The Product Owner represents their opinions.

Correct Answer:
B. B. Managers are not required at the Daily Scrum.
Explanation

The Daily Scrum is a 15-minute event for the Developers of the Scrum Team. Its purpose is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog. Management external to the Scrum Team is not required to attend. If others are present, the Scrum Master ensures they do not disrupt the meeting, which is an internal planning event for the Developers. Their role is that of an observer, and their participation is not part of the event's design.

Why Incorrect

A. The Scrum Master is a facilitator for the Developers, not a representative or spokesperson for external management.
C. The Daily Scrum is a planning session for Developers, not a status report meeting for management to receive updates.
D. The Product Owner represents stakeholders' interests in the Product Backlog, not management's opinions during the Daily Scrum.

References

1. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 9. "The Daily Scrum is a 15-minute event for the Developers of the Scrum Team... If others are present, the Scrum Master ensures that they do not disrupt the meeting."