When must a Product Owner release each Increment? (Choose the best Answer)

Full set: 298 questions
Answer options
A:

A. When it makes sense.

Correct answer
B:

B. When the Scrum Team finishes their work.

C:

C. Whenever the product is free of defects.

D:

D. After every Sprint, Without exception.

Correct Answer:
A. A. When it makes sense.
Explanation

The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team. While an Increment is created each Sprint and must be in a usable, potentially releasable state, the actual release is a business decision. The Product Owner decides when to release the Increment based on market conditions, stakeholder feedback, and overall business strategy. Therefore, an Increment is released "when it makes sense" from a value-maximization perspective.

Why Incorrect

B. The completion of work creates a potentially releasable Increment, but does not mandate an immediate release.
C. An Increment must meet the Definition of Done, but waiting for a product to be entirely free of all defects is unrealistic.
D. Releasing every Sprint is an option, but not a requirement. The Product Owner may choose to bundle several Increments for a single release.

References

1. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 6. ("The Product Owner is also accountable for effective Product Backlog management, which includes... Maximizing the value of the product...")

2. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 11. ("An Increment is a concrete stepping stone toward the Product Goal... An Increment may be delivered to stakeholders prior to the end of the Sprint.")

Scroll to Top