PSP practice question 12 of 35

Testing designed to determine whether a system is functional, has adequate sensitivity, and meets design and performance objectives accurately describes which of the following?

Full set: 312 questions

Domain Implementation of Physical Security Measures

Answer options
A: Factory acceptance testing
B: Reliability performance testing
C: Equipment performance testing
D: Site acceptance testing Correct answer
Correct Answer:
D. Site acceptance testing
Explanation

Site Acceptance Testing (SAT), also known as commissioning, is the final phase of testing performed after a security system has been fully installed and integrated at its operational location. The primary purpose of SAT is to provide a formal demonstration to the system owner that the system functions as intended. This comprehensive process verifies that the system is fully functional, its sensors and components have the required sensitivity, and it meets all the specific design criteria and performance objectives that were established in the project's requirements and design documents.

Why Incorrect

A. Factory acceptance testing: This testing is performed by the manufacturer at their facility before the system is shipped to the site to ensure it meets specifications.
B. Reliability performance testing: This is a specific type of testing focused on the system's long-term stability and ability to operate without failure over time.
C. Equipment performance testing: This is a general term that can be part of other testing phases and often focuses on individual components rather than the complete, integrated system.

References

1. ASIS International. (2012). Protection of Assets (POA)

Physical Security. Alexandria

VA: ASIS International. In the chapter "Security Project Management

" the section on "Testing and Acceptance" describes site acceptance testing as the process of verifying that the installed system meets the agreed-upon design and performance specifications in its final operational environment (pp. 428-429).

2. Garcia

M. L. (2008). The Design and Evaluation of Physical Protection Systems (2nd ed.). Butterworth-Heinemann. Chapter 10

"Performance Testing

" details the final acceptance testing process

stating it is conducted to "ensure that the as-built system meets the performance requirements specified in the design" (p. 215). This process includes functional tests and performance tests at the site.

3. International Council on Systems Engineering (INCOSE). (2015). Systems Engineering Handbook: A Guide for System Life Cycle Processes and Activities (4th ed.). Wiley. Section 5.8

"Validation Process

" describes acceptance testing as the key activity to validate that a system meets its intended use in its intended environment

which for installed systems is the Site Acceptance Test (SAT) (pp. 98-99).